CASH CUSTOMER PAYMENT SCHEDULE

Payment 01

20% + Legal Fees
  • Commitment Fee + Legal Fee
  • Immediate

Payment 02

12%
  • Upon Completion of Raft
  • Aug-18

Payment 03

12%
  • Upon Completion of 1st Floor Slab
  • Oct-18

Payment 04

12%
  • Upon Completion of 3rd Floor Slab + Commencement of Masonary Works
  • Dec-18

Payment 05

12%
  • Upon Completion of 6th Floor Slab
  • Jan-19

Payment 06

12%
  • Upon Completion of 9th Floor Slab
  • Mar-19

Payment 07

8%
  • Upon Completion of Structure
  • Apr-19

Payment 08

4%
  • Completion of All Masonary Works
  • May-19

Payment 09

4%
  • Completion of Tiling, Sanitary, Ceiling & Electrical works
  • Oct-19

Payment 10

4%
  • Upon Completion
  • Dec-19

END USER FINANCING PAYMENT SCHEDULE

Payment 01

20%+ Legal Fees
  • Commitment Fee + Legal Fee
  • Immediate

Payment 02

20%
  • Upon Completion of 1st Floor Slab
  • Oct-18

Payment 03

20%
  • Upon Completion of 4th Floor Slab
  • Dec-18

Payment 04

16%
  • Upon Completion of 9th Floor Slab
  • Mar-19

Payment 05

9.60%
  • Upon Completion of Structure
  • Apr-19

Payment 06

9.60%
  • Upon Completion of All Masonary Works
  • May-19

Payment 07

4.80%
  • Handovering
  • Dec-19